Detroit City Council gave its go-ahead for the contentious $2.2 billion proposed makeover of the Renaissance Center and East Riverfront.
After delaying a week in order to seek answers from General Motors Co. and Bedrock, council members voted 7-2 to approve about $473 million of vital tax incentives and an unprecedented $133.3 in community benefits. In addition to the public subsidies approved Tuesday, Detroit’s Downtown Development Authority has pledged $75 million in cash contributions, bringing the total public subsidies to over half a billion dollars.
City Council President James Tate and Pro Tem Coleman A. Young II as well as members Scott Benson, Angela Whitfield-Calloway, Mary Waters, Renata Miller and Latisha Johnson voted for the measures. Council Members Gabriela Santiago-Romero and Denzel McCampbell voted no.
The vote came just ahead of the council’s winter recess, and followed weeks of impassioned public debate from both sides and a flurry of information requests from council members over the mechanics and benefits tied to the complex set of agreements.
The majority of council members in support cited the promise of jobs and next-level riverfront enhancements for the city’s young people, while those opposed said they didn’t feel the deal offered Detroiters enough and that it progressed too quickly.
Related:
- RenCen seeks rebirth, visitors seek directions: A day inside Detroit landmark
- Should taxpayers pay bill for RenCen rehab?
- 2 Detroit RenCen towers could be torn down as part of new plan
District 4 Council Member Latisha Johnson said she only decided Tuesday morning to vote for the redevelopment based on a resolution crafted with Mayor Mary Sheffield’s support that would direct the $90 million the development will pay instead of taxes (payments-in-lieu-of-taxes, or PILOT) for affordable housing, neighborhood beautification and anti-poverty efforts beyond downtown and midtown.
While she had been conflicted, Johnson said she couldn’t “deprive Detroiters from being able to access jobs.”

Members Angela Whitfield-Calloway, Renata Miller and Mary Waters also spoke at length about why they are for the redevelopment plans.
Whitfield-Calloway shared some of her personal history with the RenCen, including that it was the site of her high school prom, and noted that she’d been proactive in seeking answers about the development since it was announced in 2024.
Detroiters, she said, had “never really enjoyed it (the riverfront)” in her lifetime like visitors can in other major American cities. Supporting the project, she added, would give young people something to do on the riverfront where there is currently “nothing” to do but walk from one end to the other and back.
She encouraged the developers to expedite the project — but not “cut corners” — so she and others could see it in their lifetime.
“It’s time for newness. It’s time for evolution, right? It’s time for opportunity. It’s time for opening up our horizons,” she said.
The plan calls for the $1.6 billion redevelopment of the RenCen towers, including the “deconstruction” of two of the five, and using the remaining for housing, office space and other amenities. The remaining $624 million will go toward an entertainment-centered buildout of several acres of nearby land along the East Riverfront.
Waters said that she too wanted Detroit to be a “destination place” with a, “Navy Pier like Chicago,” which she said would answer the calls of young Detroiters.
“I hope that we can all evolve to get to this place where we welcome people from all over the country, all over the world, to our city because we have such a fantastic riverfront,” Waters said.

Waters also addressed persistent complaints about the community benefits process and the recommendations put forth by the Neighborhood Advisory Council seated to negotiate on behalf of impacted neighbors of the RenCen project, saying “maybe we should not have the NAC.” She also told the audience that she’s committed to making sure developers stay accountable to their commitments.
“And, as long as God gives me the strength, I will monitor this project every step of the way. Detroiters, know that you can count on me to do exactly that,” Waters said
Miller dismissed oft-repeated “rhetoric” about the fast pace of the community benefits process, and championed the job commitments.
“This is the chance to build the best, most welcoming, family-friendly riverfront anywhere by Detroiters and for Detroiters,” Miller said.
Council members Gabriela Santiago-Romero and Denzel Anton McCampbell — whose motion to postpone the vote until the new year failed — delivered the sole ‘no’ votes on all items except the PILOT resolution brought forward by Johnson.

McCampbell said that he and his staff found more than 120 instances of language in the community benefits agreement that “lacked enforcement mechanisms,” and still wanted more benefits for residents. Santiago-Romero maintained that the council should have taken more time and called on the developers to commit to a “human-centered design.”
“If we did that, more people would be in support of this,” she said. “… I believe 90% of Detroiters want this. I believe 100% of them don’t want to feel as if they’re paying for it without their inputs.”
Critics of the RenCen redevelopment have questioned the need for public subsidies given the project is a private development. The questions have only sharpened since Dan Gilbert’s recent nearly $1 billion pledge to establish a 501(c)4 nonprofit to own and manage the redevelopment.
Bedrock’s CEO Jared Fleisher spoke before the council and to reporters on Tuesday, saying “everything is right” about the project and “everything was right about Dan’s heart and intent.”
Fleisher also apologized for calling McCampbell’s questions about the necessity of public funding “indecent,” during a recent subcommittee meeting.
GM and Bedrock sent a joint statement following the vote, saying they were grateful to the council and Sheffield’s administration, residents and the NAC for the work that led to the largest community benefits package in Detroit’s history.
Tuesday’s vote also aligns with the developers self-imposed timeline to seek state tax breaks from the Michigan Strategic Fund before Gov.-Elect Jocelyn Benson takes office in January.
‘Job wages and benefits’
Nearly every seat in the council meeting room at the Coleman A. Young Municipal Center was filled Tuesday. A majority of the nearly 200 public commenters shared their thoughts on the RenCen in the allotted half a minute of speaking time online and in-person.
People supporting and pushing back against the project repeated many of the same sentiments that have circulated for weeks. The project’s supporters — who have consistently been represented in meetings by development, business, construction and labor interests — continued to discuss the proposed benefits to Detroiters at Tuesday’s meeting.
Among the sea of pro-development attendees representing labor unions in different sets of matching high viz gear — including construction, demolition and auto unions — one benefit was king: jobs.
John Ford was one of the many Labors Local 1191 members who donned orange and touted the jobs the development would bring, pre- and post-construction.
“It’s about job wages and benefits. It’s about the future of Detroit and for my family,” Ford said. “Without it (the development), it’s like death to my family.”
Much of the remaining pro-development support came from residents, religious leaders, business owners, community and business developers, and more pleading on behalf of benefits like entertainment and tourist opportunities. Many also spoke about the benefit to the youth and Detroit’s future.
“I come from a time where the majority of downtown was abandoned, so I would dreadfully fear to see GM or the GM building become abandoned as well,” said District 5 resident Darnell Wanni.

However, the amount and security of the negotiated benefits are what the project’s many critics — as well as several of the council members — have been sharply questioning.
Residents, advocates and Santiago-Romero have said the size and complicated nature of the project and its financing more than warranted more time.
U.S. Rep. Rashida Tlaib, D-Detroit, and State Rep.-elect Chris Gilmer-Hill spoke at Tuesday’s council meeting and during a morning demonstration hosted by Detroit Action and the Detroit People’s Platform.
Tlaib joined others in championing accountability concerns and what they deemed as a lack of transparency involved in the development’s agreements and proceedings. This includes a still-confidential Law Department memo related to revenue sharing and community ownership feasibility, as well as and the non-disclosure agreement between the Detroit Economic Growth Corp. and developers that has restricted public access to the project’s financial information. Tlaib referenced the No Secret Deals Act, recent legislation she penned that would prohibit the use of such NDAs.
Only a small contingent of community members continue to ask for redevelopment to be stopped or for all five RenCen towers to be “saved.” Those speaking out against the development and developers primarily called on council to delay action until the new year in order for questions to be answered and more favorable benefits.
“Nobody here is against development,” said Detroit Action’s Alejandro Navarrete during Tuesday’s meeting, but added that opponents do take issue with “rushing the democratic process” and with “CEO bullies trying to tell us what questions we can and cannot ask” in exchange for subsidies.
“If you don’t delay and don’t do your due diligence in negotiating with the developer, then this is what we’re leaving on the table,” Navarrete said.